Scheduling a task to run on the first Monday of the month.
Date Updated  -  7/16/03
Description
User needs to schedule a task (TaskTitle = TaskX) to run on the first Monday of the month, at 6:00 AM.  Automize scheduler currently does not support this type of schedule.  However, this schedule can be obtained by using a Variable monitor task.  This solution is possible in version 5.3 and later.
Solution
1) Create an extra Variable monitor task using the following parameters:
Variable Name = $%DATE::dwm%$
Variable value = 1
Comparison Type =  equals or =
Task to Run = TaskX (i.e. task that needs to run on first Monday of month)

2) Schedule the Variable monitor task using the following parameters:
Frequency = 1
Type = Week
Date/time = 6:00 AM
Day = Monday

The first Monday of the month should always lie between dates 1-7.  The Day in Week of Month (dwm)  = 1, for dates 1-7.  i.e. the first Monday of the month should have dwm = 1.

The Variable monitor task will be triggered every Monday at 6:00 AM.  It will then check the value of the Variable 'dwm'.  If dwm = 1, it will trigger the task TaskX to run.  If dwm > 1, it will not trigger TaskX to run.  Hence the task TaskX will be run only on the first Monday of the month.