Posted: Mon Sep 16, 2013 3:04 pm Post subject: Schedule End Date |
|
|
User email support request:
We are using Automize and have noticed the most of our monthly schedule chain expire on END DATE instead of the day after END DATE for example I schedule a chain called bbb_chain to run with a START DATE of 4th September 2013 to END DATE 5th September 2013 so I expected this schedule will run until 5th September 2013 and then expire but this was not the case.
Last edited by melvin on Mon Sep 16, 2013 3:05 pm; edited 1 time in total |
|
Back to top |
|
 |
melvin Site Admin
Joined: 25 May 2006 Posts: 635 Location: Santa Barbara, california
|
Posted: Mon Sep 16, 2013 3:05 pm Post subject: |
|
|
It depends on the end date and end time.
Example:
If you set the end time as 1:00 AM , schedule would end at 1 AM on sep 4th. So any task scheduled on Sep 4th at 3 pm would not run.
But, if you set the end time as 11:59 PM, the task scheduled on Sep 4th at 3 pm would run. |
|